The Test Plan project tab shows a list of Test Plan issues and their corresponding execution status. The Test Plan status is shown as a progress bar with the latest Test Run status from each Test issue that is associated with that Test Plan. This list allows a transversal analysis of the Tests Plans for a project.
Image Removed
The Test Plans page is headlined by the Test Plans Filter that allows the user to search by:
the Fix Version tested by the a Test Plan the selected Project is associated with
the Status of the Test Plan the selected Project is associated with
the Issue Key or Summary of a Test Plan
The search results are displayed on the table immediately under the Test Plan Filter, which contains:
the Test Plan issue Key of the listed Test Plan the selected Project is associated with
the Summary of the listed Test Plan the selected Project is associated with
the Start and End dates of the listed Test Plan the selected Project is associated with
the Fix Version tested by the a Test Plan the selected Project is associated with
the Execution Status of the listed Test Plan the selected Project is associated with
From each Test Plan row, it is possible to perform some quick actions by clicking the Gear button. The actions showed below are available.
UI Step
We can Edit
Using the the Gear button you can jump to the Test Plan issue Edit page;
Screenshot: Example Test issue Edit page
Image Removed
This gadget provides a summary of the filtered Test Runs, in chart or table layout, showing the amount of Test Runs per status, grouped by a given Test or Test Run field.
Image Added
UI Step
Purpose
This gadget enables you to see the overall status of a group of scheduled/executed Test Runs (e.g., from a Test Plan) through a vertical bar chart or a table, showing the amount of Test Runs per status, grouped by a given Test or Test Run field.
Some possible usage scenarios:
analyze the Test Runs from a Test Execution
analyze the Test Runs from all Test Executions belonging to a Test Plan
depict the testing results for a given component, in the context of a Test Execution or Test Plan
see how the testing is progressing in terms of scheduled runs, from the Test Run assignee perspective
see how the testing is progressing in terms of scheduled runs, based on the Test priority
see how failures, or some other test run statuses, are impacting components
UI Step
How to use
Source Test Runs for the chart can be indirectly provided using a saved filter or selected Test Execution and Test Plans, which may be used in conjunction with Test and Test Run-specific filters:
Saved filter or Issue Picker: a saved filter containing Test Execution and/or Test Plans issues or a selection of said issues; This field is mandatory
Test Filters:
Priority: priority of the Test associated with the Test Run
Test Run Filters:
Assignee: assignee of the Test Run
Status: status of the Test Run
Date range: only Test Runs with start date and end date between the selected range will be considered
Additional configuration parameter for this gadget include:
Group By: group the results by the Test Run assignee, Test Run executed by, Test component, Test Key, Test Type, label, priority and any custom field with options.
UI Step
Examples
Image Added
Image Added
UI Step
We can delete
Using the the Gear button you can jump to the Test Plan issue Delete Issue dialogue page