  • Date Range: either Custom, Time frame or Planned dates from Test Executions
    • if "Custom", then you need to provide the dates of the time period:
      • Start date and End date: only the Test Runs with start date and end date between this range will be considered
    • if "Time frame", then it can be either:
      • Current Week
      • Last Week
      • Current Month
      • Last Month
      • Last Days
    • if "Planned dates from Test Executions", then the minimum and maximum of begin and end dates, respectively, from the Test Executions are considered 
  • Test Run Assignee: the user assigned to the Test Run
    • Current User: option to choose dynamically the current user logged in as the selected user when sharing dashboards with others. Please note that in confluence, the current user will always be the user that owns the connection between Confluence and Jira.
  • Test Run Status: the status of the Test Run
  • Test Environment: the Test Environment to take into account (i.e., only consider the Test Runs from Test Executions made for this environment)

...