Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Table of Contents


Xray uses different issue types for implementing the testing process (with the exception of Test Runs).

...

Issue typePurposeNotes
Test
  • estimated execution duration for this Test
  • estimated specification time for this Test
using "estimated execution time" may be more adequate; however if you choose that approach, you may have to decide where to report the estimation for the specification (e.g. in a Test Set or in some specificaiton task)
Pre-Condition
  • estimated execution duration for this Pre-Condition
  • estimated specification time for this Pre-Condition
see notes for Test issue
Test Setestimated time for specifying all the Tests being grouped within this Test Set
(Sub)Test Executionestimated time for running all related Test Runs
Test Plan
  • estimated time related only with environment setup, planning
  • estimated time for all the effort associated with the validation of the Tests within the plan, including environment setup and multiple iterations
your estimated time aim for the Test Plan should match the aim of the logged time

Comparisons

At individual Test Run level, original estimated vs effective elapsed time

For obtaining the elapsed time for each Test Run, you may use the Test Runs Report. Then you may export it to CSV.

You would need however to export also Test issues from the Issue search page and show the "Original Estimate" field. Then you could cross the two results in order to have a one-to-one comparison.

At Test Execution level, comparing the sum of the estimated times for each Test vs the sum of the elapsed time for all the Test Runs

In this case we compare estimations on Test issues against the actual elapsed time (not the logged time/work logs on the Test Execution).

In order to obtain the "the sum of the estimated times for the Tests that are part of the Test Execution", we can either do an Issue Search based on the Tests and show the Original Estimate column, or we can use an additional add-on to build a calculated custom field.  sumUp add-on is a good solution for that.

With "sumUp" you may define a rule and then you can use a custom field which calculates the value based on it.

a) create a configuration

Image Added

b)  create a custom field (e.g. "TestsEstimation") of type "SumUp Text" and configure it to use the "Estimation" created previously; associate it to the Test Execution screens

Image Added

Image Added


Then in Issues search page, that information can be seen as a column.

Image Added

  

In order to obtain the sum of the elapsed time, you may use the "Test Executions Report", which you can export to CSV if you wish to cross the values.


At Test Execution level, comparing the sum of the estimated times for each Test vs the sum of the logged time (work logs)

In this case we assume people log time on the Test Execution issues which we want to compare against the estimations made on the Test issues.

In order to obtain the "the sum of the estimated times for each Test", we can follow the same approach we did in 2) for creating a calculated custom field with its value.

We can then just compare that value of that custom field (e.g. "TestsEstimation") to the "Time Spent" directly. 

If you prefer to use estimation on the Test Execution field, you may use the "TestsEstimation" as an auxiliary field for filling out the value of the "Original Estimate" on the Test Execution. Then you can use the standard "Original Estimate" vs "Time Spent" comparisons.

Image Added

Recommendations

Using time estimates and logging time depend on your use case. You can choose to use both or just one of them.

...