Page History
...
- This takes into account Test Runs in version V (as a result of Test Executions in version V) or Test Runs in Test Plan TP (within Test Executions associated with Test Plan TP)
- If Test Environment is chosen, then only Tests Runs on that Environment (e.g. TE) will be considered
- If "Final statuses have precedence over non-final statuses" is true, then:
- final Test Run statuses will have higher ranking than non-final ones
- only the latest Test Run is taken into account based on its "finished on" date
- If "Final statuses have precedence over non-final statuses" is false, then:
- only the latest Test Run is taken into account based on its "created" date (i.e. the creation date of the related Test ExecutionRun entity - this happens when a Test Run is first executed, or when the user navigates into the execution screen)
Calculate the status of some Test, in version V or Test Plan TP, for "All Environments"
...